1 Hastings Pde, Bondi.
Site Progress
Brickwork continues to be removed.
Footings commenced for East / South boundary of property.
Contiguous piles continued and capping beam prepared.
Programmed works
Continue removal of building brickwork.
Continue contiguous piles around western side of car park area.
Commence preparation for piling of property footings.
Pour capping beam of car park area.