Henrietta St, Waverley.
Site Progress
Carpentry – House 1 / 2 / 3 / 4: o Box outs and window trims prepared for window install.
Plumbing – House 1 / 2: o OSD tank and pipes installed for House 3 / 4. o Sewer lines for Rear property re-connected.
Driveway demolition continued. • Driveway under footings and dincel walls formed and poured, to support underside of driveway, near rear adjacent property.
Rendering/ painting of wall nibs on house 1 / 2 for preparation of glass doors.
Window delivery and install of sub head and sills on all houses.
Steel delivered for driveway slab.
Scaffolding erected for the neighbour’s access to their property (rear).
House 1 / 2 Carpentry – stud walls on laundry variations for House 3 / 4.
Driveway – Demolition to continue. • Driveway slab to be formed and poured.
All house windows to be installed and complete.
Retaining wall footing between House 1 / 2 and 3 / 4 to prepared.
House 1 / 2 external CFC to be installed.
Electrical rough-in to commence on House 1 / 2.
Plumbing rough-in to continue.